Skip Ribbon Commands
Skip to main content
Sign In

Title

STATUS UPDATE 1: B11 PIPELINE SHUTDOWN

Body

Rand Water would like to inform the media of the progress being made with respect to the shutdown of its B11 Pipeline.
 
Activity 1: Isolation of the Pipeline and drainage of the water 
 
This activity commenced on schedule today at 6:00am and will be completed at 22h00 today.  This 12km pipeline is 2500mm in diameter, from where significant volumes of water need to be drained.  The draining of water will allow technicians to safely commence with the required cutting and welding aspect of the work.  This activity is proceeding according to schedule.  The isolation is complete and the line is being drained. All the required resources are on site i.e. valve, crane and required skilled human resources etc.
 

 

Expires

24/06/2019

Attachments

Created at 24/06/2019 5:47 p.m. by System Account
Last modified at 25/06/2019 11:18 a.m. by System Account
Home Contact Us Legal Notice Site Map