08H30
The work on the B11 Shutdown proceeded successfully throughout last night. A new shift of technicians took over this morning to finalise the welding aspects of the project. At this time, the project is on target to complete the necessary welding work within the 54 hour schedule. Thereafter, the normal processes of commissioning the line will commence.